Establishment capital is concentrated in planting material, land preparation and the water system.
Low 386.5 k€
€9,663/ha
Base 498.5 k€
12.5 k€/ha
Conservative 625.0 k€
15.6 k€/ha
Project payback Year 9
First year in which cumulative project cash flow turns positive
Establishment CAPEX
Budget under three cost scenarios for the 40 ha.
| Category | Low (€) | Base (€) | Conservative (€) | % of base | €/ha base |
|---|---|---|---|---|---|
| Soil, water, topography studies and agronomic design | 500 | 1,000 | 1,500 | 0.2% | 25 |
| Land preparation and base soil correction | 100,000 | 130,000 | 160,000 | 26.1% | 3,250 |
| Grafted plants | 166,000 | 190,000 | 220,000 | 38.1% | 4,750 |
| GPS layout and planting | 12,000 | 16,000 | 20,000 | 3.2% | 400 |
| Stakes, guards and fixings | 14,000 | 19,500 | 22,500 | 3.9% | 488 |
| Irrigation and fertigation network | 30,000 | 35,000 | 40,000 | 7.0% | 875 |
| Abstraction, reservoir and pumping | 33,000 | 36,000 | 40,000 | 7.2% | 900 |
| Fencing and internal access tracks | 0 | 15,000 | 25,000 | 3.0% | 375 |
| Electrification, solar and switchboards | 15,000 | 25,000 | 40,000 | 5.0% | 625 |
| Weather station and sensors | 0 | 1,000 | 2,000 | 0.2% | 25 |
| Engineering, design and permits | 6,000 | 10,000 | 14,000 | 2.0% | 250 |
| Contingency | 10,000 | 20,000 | 40,000 | 4.0% | 500 |
| Total | 386,500 | 498,500 | 625,000 | 100 % | 12,463 |
Base CAPEX composition
Operating costs
The first five years are the establishment phase, with no revenue. Cost per hectare rises as the orchard comes into production.
OPEX for the first 5 years
| Year | Low | Base | Conservative |
|---|---|---|---|
| 1 | 20,000 | 32,000 | 40,000 |
| 2 | 20,000 | 32,000 | 40,000 |
| 3 | 20,000 | 32,000 | 40,000 |
| 4 | 20,000 | 32,000 | 40,000 |
| 5 | 20,000 | 32,000 | 40,000 |
| Total | 100,000 | 160,000 | 200,000 |
Includes irrigation and energy, fertilisation, weed control, treatments, pruning and replanting.
OPEX evolution over 30 years
Project cash flow
Annual and cumulative project cash flow, including the initial investment in year 0, reinvestments and annual income support.